Friday, August 29, 2008

Aug 29 Update

Today’s update doesn’t show a lot of major changes, but things are still going well. The drywall crew is getting to the end of their job with only a few small areas left to rock and the south side is getting mud and tape this week. Most of the furnaces are installed and the new wiring is getting pulled through the conduit.

On Saturday, September 6th we’ll be having a church-wide workday where we’ll need a lot of people to help with cleaning and prepping for the painters who will hopefully start painting around Tuesday the 9th. We’ll also need a crew of carpenters to do various construction projects throughout the facility. An announcement will be coming this weekend in services and we’ll also send out an email early in the week.

Below are a few pictures from this morning:

Grass has been seeded on the southwest side of the facility.



Here's the nursery area.



Outside the nursery the main hallway is now lit.



Here's an example of the electrical work that still needs to be done.



In the atrium, the brick columns have now been replaced by drywall air returns.



New furnace units.



A bare spot awaiting a new large electrical panel.



The southeast hallway with wire spools being used by the electrician.



The gym stage now drywalled and ready to be decked.